        PROJECT NAME:   Upgradation of the Distribution System including inst of new substations at strategic locations and strengthening of Ring Main, Gangtok
                 PROJECT ID:   1368
(Amount in Lakhs)

                SECTOR NAME:   POWER DEVELOPMENT
                SUB SECTOR NAME:   POWER DEVELOPMENT
                SCHEME NAME:   
                PROJECT LOCATION:   Gangtok
                PIN CODE:   
                LATITUDE:   
                LONGITUDE:   
                STATE NAME:   Sikkim
                PROJECT CATEGORY:   State Govt. Project
                PROJECT TYPE:   Not Applicable
                PROJECT/NON PROJECT:   Project
                COMPONENT:   None
                OBJECTIVE:   
                DESCRIPTION:   
                ESTIMATED COST:   491.53
                REVISED COST:   491.53
                APPROVED COST:   491.53
                APPROVAL NUMBER:   NEC/POW/490/2009-10/2394
                APPROVAL DATE:   2009-12-09
                NEC SHARE:   442.38
                STATE SHARE:   49.15
                TARGET DATE OF COMPLETION:   
                ACTUAL DATE OF COMPLETION:   
                PROJECT STATUS:   Completed
                OM No:   
                Pre 2007-08 Releases
                No records found!
                Post 2007-08 Sanctions
                Number of Post 2007-08 Sanctions: 3
Implementing Agency Sanction No Sanction Date Amount Instalment No Functional Head Obj.Head Fin.Year Finance Vetting No Finance Vetting Date Remarks
1 E&P Department, Govt. of Sikkim NEC/POW/490/2009-10/2395 2009-12-09 200.00 1 3601051010200 31 2009-2010 265 2009-12-04 Not Specified
2 E&P Department, Govt. of Sikkim NEC/POW/490/2009-10/2511 2011-03-08 180.00 2 3601051010200 35 2010-2011 450 2011-02-28 Not Specified
3 E&P Department, Govt. of Sikkim NEC/POW/490/2009-10/3019 2013-11-12 62.38 3 3601051010200 35 2013-2014 226 2013-11-07 3rd installment
Total442.38
                Post 2007-08 Releases
                Number of Post 2007-08 Releases: 3
Implementing Agency Sanction No & Date Released Amount & Date PFMS Advice No & Date Instrument in favour of Func.Head Obj.Head Fin.Year Share NEC Share Utilized Amount State Share Released Amount & Date State Share Utilized Amount UC Filed Date UC Status
1 E&P Department, Govt. of Sikkim NEC/POW/490/2009-10/2395
2009-12-09
200.00
2010-01-06
154512
2010-01-04
Not Specified 3601051010200 31 2009-2010
2 E&P Department, Govt. of Sikkim NEC/POW/490/2009-10/2511
2011-03-08
180.00
2011-03-15
A460649
2011-03-15
Not Specified 3601051010200 35 2010-2011
3 E&P Department, Govt. of Sikkim NEC/POW/490/2009-10/3019
2013-11-12
62.38
2013-11-27
A013881
2013-11-27
Not Specified 3601051010200 35 2013-2014
Total442.38
                Implementing Agency
                      Agency Name: E&P Department, Govt. of Sikkim