The NorthEast India
North Eastern Council
Utilization Certificate Portal(Reports)

NEC Project Details

        PROJECT NAME:   Construction of 33kV Line from Pakke to Chayangtajo including 2x1 MVA, 33/11 kV Substation at Chayangtajo, East Kameng District, Arunachal Pradesh.
                 PROJECT ID:   2233
(Amount in Lakhs)

                SECTOR NAME:   POWER DEVELOPMENT
                SUB SECTOR NAME:   POWER DEVELOPMENT
                SCHEME NAME:   
                PROJECT LOCATION:   East Kameng District
                PIN CODE:   
                LATITUDE:   
                LONGITUDE:   
                STATE NAME:   Arunachal Pradesh
                PROJECT CATEGORY:   State Govt. Project
                PROJECT TYPE:   Not Applicable
                PROJECT/NON PROJECT:   Project
                COMPONENT:   None
                OBJECTIVE:   
                DESCRIPTION:   
                ESTIMATED COST:   0.00
                REVISED COST:   0.00
                APPROVED COST:   489.52
                APPROVAL NUMBER:   NEC/POW/AP/558/2012-13/2836
                APPROVAL DATE:   2012-11-08
                NEC SHARE:   440.57
                STATE SHARE:   48.95
                TARGET DATE OF COMPLETION:   
                ACTUAL DATE OF COMPLETION:   
                PROJECT STATUS:   Completed
                OM No:   
                Pre 2007-08 Releases
                No records found!
                Post 2007-08 Sanctions
                Number of Post 2007-08 Sanctions: 3
Implementing Agency Sanction No Sanction Date Amount Instalment No Functional Head Obj.Head Fin.Year Finance Vetting No Finance Vetting Date Remarks
1 Power Deptt., Govt. of AP NEC/POW/AP/558/2012-13/2837 2012-11-08 180.00 1 3601051010200 35 2012-2013 269 2012-10-31 Not Specified
2 Power Deptt., Govt. of AP NEC/POW/AP/558/2012-13/3088 2014-03-14 170.00 2 3601051010200 35 2013-2014 483 2014-03-07 Not Specified
3 Power Deptt., Govt. of AP NEC/POW/AP/558/2012-13/6100 2018-12-14 90.57 3 3601081030100 35 2018-2019 454 2018-12-10 3& final installment
Total440.57
                Post 2007-08 Releases
                Number of Post 2007-08 Releases: 3
Implementing Agency Sanction No & Date Released Amount & Date PFMS Advice No & Date Instrument in favour of Func.Head Obj.Head Fin.Year Share NEC Share Utilized Amount State Share Released Amount & Date State Share Utilized Amount UC Filed Date UC Status
1 Power Deptt., Govt. of AP NEC/POW/AP/558/2012-13/2837
2012-11-08
180.00
2012-11-19
Adv.No.193
2912-11-19
Not Specified 3601051010200 35 2012-2013
2 Power Deptt., Govt. of AP NEC/POW/AP/558/2012-13/3088
2014-03-14
170.00
2014-03-26
Adv. No. 447
2014-03-26
Not Specified 3601051010200 35 2013-2014
3 Power Deptt., Govt. of AP NEC/POW/AP/558/2012-13/6100
2018-12-14
90.57
2018-12-20
Advice:210
2018-12-20
Not Specified 3601081030100 35 2018-2019
Total440.57
                Implementing Agency
                      Agency Name: Power Deptt., Govt. of AP
                      Agency Id: 91