SECTOR NAME:
POWER DEVELOPMENT |
|
SUB SECTOR NAME:
POWER DEVELOPMENT |
|
SCHEME NAME:
|
|
PROJECT LOCATION:
Agia (Assam), Nangalbibra (Megh) |
|
PIN CODE:
|
|
LATITUDE:
|
|
LONGITUDE:
|
|
STATE NAME:
Meghalaya |
|
PROJECT CATEGORY:
State Govt. Project |
|
PROJECT TYPE:
Not Applicable |
|
PROJECT/NON PROJECT:
Project |
|
COMPONENT:
None |
|
OBJECTIVE:
|
|
DESCRIPTION:
|
|
ESTIMATED COST:
4332.00 |
|
REVISED COST:
4332.00 |
|
APPROVED COST:
4332.00 |
|
APPROVAL NUMBER:
NEC/POW/227/97-98/VOL-IV/994 |
|
APPROVAL DATE:
19-03-2007 |
|
NEC SHARE:
3898.80 |
|
STATE SHARE:
433.20 |
|
TARGET DATE OF COMPLETION:
|
|
ACTUAL DATE OF COMPLETION:
|
|
PROJECT STATUS:
Completed |
|
OM No:
|
|
|
Pre 2007-08 Releases
|
Number of Pre 2007-08 Releases: 1
|
|
Implementing Agency
|
Approval No
|
Approval Date
|
Sanction No
|
Sanction Date
|
Released Amount
|
Finance Vetting No
|
Finance Vetting Date
|
Functional Head
|
Obj.Head
|
Fin.Year
|
Instalment No(pre 2007-08)
|
Remarks
|
1
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98, Vol-IV/994
|
19-03-2007
|
No.NEC/POW/227/97-98, Vol-IV/996
|
19-03-2007
|
1080.00
|
678
|
08-03-2007
|
3601051010200
|
31
|
2006-2007
|
1
|
On-going scheme
|
|
|
|
Post 2007-08 Sanctions
|
Number of Post 2007-08 Sanctions: 4
|
|
Implementing Agency
|
Sanction No
|
Sanction Date
|
Amount
|
Instalment No
|
Functional Head
|
Obj.Head
|
Fin.Year
|
Finance Vetting No
|
Finance Vetting Date
|
Remarks
|
1
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/Vol.IV/2179
|
25-03-2008
|
1438.24
|
2
|
3601051010200
|
31
|
2007-2008
|
Not Specified
|
01-01-1970
|
2nd installment
|
2
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/Vol.IV/2353
|
11-09-2009
|
900.00
|
3
|
3601051010200
|
31
|
2009-2010
|
89
|
04-06-2009
|
Not Specified
|
3
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/Vol.IV/2466
|
16-09-2010
|
450.00
|
4
|
3601051010200
|
35
|
2010-2011
|
144
|
14-09-2010
|
Not Specified
|
4
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/VOL-IV/4043
|
13-06-2014
|
30.56
|
5
|
3601051010200
|
35
|
2014-2015
|
130
|
06-06-2014
|
5th & final installment
|
Total | | 2818.80 | |
|
|
|
Post 2007-08 Releases
|
Number of Post 2007-08 Releases: 4
|
|
Implementing Agency
|
Sanction No & Date
|
Released Amount & Date
|
PFMS Advice No & Date
|
Instrument in favour of
|
Func.Head
|
Obj.Head
|
Fin.Year
|
Share
|
NEC Share Utilized Amount
|
State Share Released Amount & Date
|
State Share Utilized Amount
|
UC Filed Date
|
UC Status
|
1
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/Vol.IV/217925-03-2008
|
1438.2422-04-2008
|
77764631-03-2008
|
Not Specified
|
3601051010200
|
31
|
2007-2008
|
|
2
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/Vol.IV/235311-09-2009
|
900.0029-09-2009
|
Not Specified
|
Not Specified
|
3601051010200
|
31
|
2009-2010
|
|
3
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/Vol.IV/246616-09-2010
|
450.0008-10-2010
|
As per CPSMS Advice No.278
|
Not Specified
|
3601051010200
|
35
|
2010-2011
|
|
4
|
Meghalaya Electricity Corporation Ltd.
|
NEC/POW/227/97-98/VOL-IV/404313-06-2014
|
30.5619-06-2014
|
Advice No:4319-06-2014
|
Not Specified
|
3601051010200
|
35
|
2014-2015
|
|
Total | | 2818.80 | |
|
|
|
Implementing Agency
|
Agency Name: Meghalaya Electricity Corporation Ltd.
|
Agency Id: 305
|