The NorthEast India
North Eastern Council
Utilization Certificate Portal(Reports)

     
Implementing Agency Details

        AGENCY NAME:   Tripura State Electricity Corporation Ltd.
                 AGENCY ID:   369
     Additional Details

                SECTOR NAME:   POWER DEVELOPMENT
                ADDRESS:   Tripura
                STATE NAME:   Tripura
                CONTACT PERSON:   Chairman-cum-Managing Director
                PHONE NO:   9436122643
                FAX NO:   03812351579
                EMAIL ID:   agmtc11@gmail.com
                WEBSITE:   www.tsecl.in
                AGENCY CATEGORY:   Public Sector Company
                Administrative Approvals
                  Number of Approvals so far: 7
                  Amount Approved so far: 57064.64 Lakhs
                Pre 2007-08 Releases
                      No records found!
                Post 2007-08 Sanctions
                Number of Post 2007-08 Sanctions so far: 25
                      Total Post 2007-08 Sanctioned Amount for Func.Head 3601051010200 & Obj.Head 31 : 6720.6 Lakhs
                      Total Post 2007-08 Sanctioned Amount for Func.Head 3601051010200 & Obj.Head 35 : 4780.53 Lakhs
                Post 2007-08 Releases
                Number of Post 2007-08 Releases so far: 25
                      Total Post 2007-08 Released Amount for Func.Head 3601051010200 & Obj.Head 31 : 6720.6 Lakhs
                      Total Post 2007-08 Released Amount for Func.Head 3601051010200 & Obj.Head 35 : 4780.53 Lakhs
                Projects Involved
                Number of projects so far: 7
                      121 MW Baramura (Unit-V) Gas Based Thermal Project
                      2Augmentation by addition of 132/11kV, 1x12.5 MVA, Transformer along with associated equipments at 132kV Udaipur Substation, South Tripura
                      3Augmentation of Sub Station Capacity by addition of 1x20/25 MV,132/33kV Transformer along with associated Civil Work at Ambassa, Dhalai District, Tripura
                      4Augmentation by addition of 132/33kV,1x20/25 MVA, Transformer along with associated equipments and civil works at 132kV Mission Tilla Substation, Dharmanagar, Tripura
                      5Construction of 2X10MVA 132/33KV and 2X10MVA, 33/11KV Sub-station including LILO at Bishramganj, Sepahijala District, Tripura.
                      6Augmentation by capacity addition of 1X20/25 MVA, 132/33kV transformer and 2X12.5MVA, 132/11kV transformer with associated equipments at Mission Tilla 132kV Sub-Station, Dharmanagar, North Tripura
                      7Construction of 132kV SC Transmission Line from 132kV Ambassa substation to Gandacherra Substation Tripura