Administrative Approvals
|
Number of Approvals so far: 7
|
Amount Approved so far: 57064.64 Lakhs
|
|
|
|
Pre 2007-08 Releases
|
No records found!
|
|
|
|
Post 2007-08 Sanctions
|
Number of Post 2007-08 Sanctions so far: 25
|
Total Post 2007-08 Sanctioned Amount for Func.Head 3601051010200 & Obj.Head 31 : 6720.6 Lakhs
|
Total Post 2007-08 Sanctioned Amount for Func.Head 3601051010200 & Obj.Head 35 : 4780.53 Lakhs
|
|
|
|
Post 2007-08 Releases
|
Number of Post 2007-08 Releases so far: 25
|
Total Post 2007-08 Released Amount for Func.Head 3601051010200 & Obj.Head 31 : 6720.6 Lakhs
|
Total Post 2007-08 Released Amount for Func.Head 3601051010200 & Obj.Head 35 : 4780.53 Lakhs
|
|
|
|
Projects Involved
|
Number of projects so far: 7
|
121 MW Baramura (Unit-V) Gas Based Thermal Project
|
2Augmentation by addition of 132/11kV, 1x12.5 MVA, Transformer along with associated equipments at 132kV Udaipur Substation, South Tripura
|
3Augmentation of Sub Station Capacity by addition of 1x20/25 MV,132/33kV Transformer along with associated Civil Work at Ambassa, Dhalai District, Tripura
|
4Augmentation by addition of 132/33kV,1x20/25 MVA, Transformer along with associated equipments and civil works at 132kV Mission Tilla Substation, Dharmanagar, Tripura
|
5Construction of 2X10MVA 132/33KV and 2X10MVA, 33/11KV Sub-station including LILO at Bishramganj, Sepahijala District, Tripura.
|
6Augmentation by capacity addition of 1X20/25 MVA, 132/33kV transformer and 2X12.5MVA, 132/11kV transformer with associated equipments at Mission Tilla 132kV Sub-Station, Dharmanagar, North Tripura
|
7Construction of 132kV SC Transmission Line from 132kV Ambassa substation to Gandacherra Substation Tripura
|
|
|