        PROJECT NAME:   21 MW Baramura (Unit-V) Gas Based Thermal Project
                 PROJECT ID:   457
(Amount in Lakhs)

                SECTOR NAME:   POWER DEVELOPMENT
                SUB SECTOR NAME:   POWER DEVELOPMENT
                SCHEME NAME:   
                PROJECT LOCATION:   Tripura
                PIN CODE:   
                LATITUDE:   
                LONGITUDE:   
                STATE NAME:   Tripura
                PROJECT CATEGORY:   State Govt. Project
                PROJECT TYPE:   Not Applicable
                PROJECT/NON PROJECT:   Project
                COMPONENT:   None
                OBJECTIVE:   
                DESCRIPTION:   
                ESTIMATED COST:   9972.00
                REVISED COST:   9972.00
                APPROVED COST:   8000.00
                APPROVAL NUMBER:   NEC/POW/312/2002-04/VOL.IV/1042
                APPROVAL DATE:   2007-08-29
                NEC SHARE:   7200.00
                STATE SHARE:   800.00
                TARGET DATE OF COMPLETION:   
                ACTUAL DATE OF COMPLETION:   
                PROJECT STATUS:   Completed
                OM No:   
                Pre 2007-08 Releases
                No records found!
                Post 2007-08 Sanctions
                Number of Post 2007-08 Sanctions: 5
Implementing Agency Sanction No Sanction Date Amount Instalment No Functional Head Obj.Head Fin.Year Finance Vetting No Finance Vetting Date Remarks
1 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/1098 2007-11-02 1000.00 1 3601051010200 31 2007-2008 206 2007-11-01 1st installment
2 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/2203 2008-06-04 2000.00 2 3601051010200 31 2008-2009 50 2008-05-22 2nd installment
3 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/2309 2009-03-19 1220.60 3 3601051010200 31 2008-2009 366 2009-03-13 Not Specified
4 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol-IV/2343 2009-07-29 2500.00 4 3601051010200 31 2009-2010 35 2009-07-22 Not Specified
5 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/2504 2011-02-15 479.00 5 3601051010200 35 2010-2011 404 2011-02-15 Not Specified
Total7199.60
                Post 2007-08 Releases
                Number of Post 2007-08 Releases: 5
Implementing Agency Sanction No & Date Released Amount & Date PFMS Advice No & Date Instrument in favour of Func.Head Obj.Head Fin.Year Share NEC Share Utilized Amount State Share Released Amount & Date State Share Utilized Amount UC Filed Date UC Status
1 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/1098
2007-11-02
1000.00
2007-12-07
Not Specified
1970-01-01
Secretary, Finance Deptt. Govt. of Tripura 3601051010200 31 2007-2008
2 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/2203
2008-06-04
2000.00
2008-07-29
Not Specified
1970-01-01
The Secretary, Finance Department, Govt. of Tripura 3601051010200 31 2008-2009
3 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/2309
2009-03-19
1220.60
2009-03-25
417249
2009-03-25
Secy. Finance Dept. Govt. of Tripura 3601051010200 31 2008-2009
4 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol-IV/2343
2009-07-29
2500.00
2009-08-24
govt Code120
1970-01-01
AG(Audit)Tripura/Secy Finance Dept. Govt. of Tripura 3601051010200 31 2009-2010
5 Tripura State Electricity Corporation Ltd. NEC/POW/312/2002-03/Vol.IV/2504
2011-02-15
479.00
2011-02-21
Not Specified
1970-01-01
Finance Secy, Govt. of Tripura 3601051010200 35 2010-2011
Total7199.60
                Implementing Agency
                      Agency Name: Tripura State Electricity Corporation Ltd.
                      Agency Id: 369